Floating Photovoltaic Power Plants

World’s first use in 2012

  1. 01 2009 Juam Dam 2.4kW Experimental Model
  2. 02 2011 Hapcheon Dam 100kW demonstration model
  3. 03 2012 Hapcheon Dam 500kW first commercialization
  4. 04 Hapcheon Dam 100kW research model
  5. 05 Water quality Low-quality organisms Birds Pisces Environmental safety verification
  6. 06 2016 Boryeong Dam 2MW
  7. 07 2017 Chungju Dam 3MW
  8. 08 2022 Chungju Dam 2.6MW

Creating new value for water energy through community
participation projects sharing generation revenue.

  • Hapcheon Dam SPC
    • Capacity41.5MW
    • CompletionNov `21
    • LocationHapcheon, Gyeongnam
  • Soyanggang Dam Yanggu SPC
    • Capacity8.8MW
    • CompletionNov `23
    • LocationYanggu, Gangwon
  • Imha Dam SPC
    • Capacity47.2MW
    • CompletionJul ‘25
    • LocationAndong, Gyeongbuk
맨 위로